INTRODUCTION
Austin Energy is the nation’s eighth
largest publicly-owned electric utility and a department of the City of Austin.
The mission is to deliver clean, affordable, reliable energy and excellent
customer service. Our utility provides electricity to more than 420,000
customers and a population of almost one million in the City of Austin, several
neighboring cities, unincorporated areas of Travis County, and a portion of
Williamson County. The company operations are funded entirely through energy sales
and services, and Austin Energy supports other City of Austin services with an
annual transfer into the general fund of more than $100 million. The utility
operates within the ERCOT market. The mission is to deliver clean, affordable,
reliable energy and excellent customer service.
Austin Energy is recognized for achieving
some of the highest performance standards in the industry. These standards
include aggressive renewable and reliability goals and demonstrated efforts to
promote new clean energy technologies and a sustainable environment. The City
of Austin’s goals for use of renewable energy are some of the most aggressive
in the United States. Austin Energy ranks first among Texas utilities for green
power sales. Austin Energy also offers some of the most comprehensive energy
efficiency programs in America. Austin Energy has long recognized the
environmental and energy benefits of electric vehicles. The company leading the
effort to study the impact of electric vehicles on the electric system while promoting
increased market share in the automotive industry.
STRENGTH
- - Rates are affordable, competitive, and stable
- - Company commitment to clean energy resources. Austin Energy has a diverse generation portfolio of nearly 3,000 megawatts. This diverse mix of generation fueled by wind, solar, biomass, natural gas, nuclear, and coal helps Austin Energy control costs and power plant emissions.
- - Affordable. Austin Energy has an established goal to maintain rates in the lower 50 percent among comparable Texas utilities.
- - Reliable. Austin Energy provides exceptional electric system reliability and significant expertise in serving power-sensitive industries such as high-tech manufacturing.
- - Excellent Customer Service. Austin Energy’s Electric Service Delivery, Power Supply and Market Operations, and Customer Care groups are ISO 9001:2008 certified by the International Organization for Standardization.
WEAKNESS
- - Instability issues. Persistent system error from billing department
- - Customer services employee. Employee response one to one assistant for account accessing and correcting error.
- - Customer. Unable to access system online portal, system causes a lot of problem, not friendly and hard time for customer.
- - IBM failure. Billing software system failure
OPPORTUNITY
- - Austin Energy customers can influence policy makers
- - Policies reflect community values and priorities
- - Annual dividends go to the community
- - Austin Energy supports the local economy
- - Local control, Austin Energy is able to make business decisions that are important to customers — such as investing dollars in electric system reliability and allocating millions of dollars to help low-income residents pay their utility bills.
- - Local control also helps Austin Energy to prioritize energy efficiency programs and to support our clean power strategy for reduced emissions and sustainable power supplies.
- - Local ownership also allows for collaboration with clean tech companies that are developing advanced energy management systems and growing green jobs.
THREAT
- - Modernization billing project delays. Austin and IBM project late completion, delay schedule, software bugs
- - Software bugs. Error of thousand of bills, 65000 never received bills, 35000 in accurate bills, overcharging
SUGGESTION AND ACTION
QUESTION 1 :
Is Austin Business Project is a failure?
ANSWER:
Yes, the Austin Business Project is failure
because :
Modernization billing project delays
• Austin
and IBM project late completion, delay schedule, software bugs
• Complexity
new billing system with 73 different interface
Software bugs
• Error
of thousand of bills
• 65000
never received bills
• 35000
in accurate bills, overcharging
Instability issues
• Seriously
impact business and customer
• Persistent
system error from billing department
• Revenue
loses
Customer services employee
• Employee
response one to one assistant for account accessing and correcting error.
• Called
them selves as alpha tester
Customer
• Unable
to access system online portal
• System
causes a lot of problem, not friendly and hard time for customer.
IBM failure
• Billing
software system failure
QUESTION 2 :
Describe the business impact
of the faltering Austin Energy project.
ANSWER:
Operation
• Mostly
affected is billing department.
• Difficulties
of issuing bills because of billing software failure.
• Common
error of customer not received bills, customer receive in accurate bills,
account automatically cancelled.
• Incurred
more cots in utilities and operation. Since business function is
interconnected, one function failure give impact of another function such as
production.
• Business
service is inaccurate, it give impact in revenue and profit even though they
don’t have pressure of competitor.
Customer service
• The
department mostly affected.
• Employee
work in high level of stress.
• Extra
effort need to solve customer problem. They still need to serve customer better
even though customer angry to show their disappointment towards the company.
• Employee
also treated in the same way as usual, do not receive any appreciation from the
company.
• Give
impact of public relationship disaster.
Sales and marketing
• Company
also faced difficulties in determining the actual sales since the system leads
more error.
• Sales
and profit decreasing.
• Company
might face law suit for this issues. If it is happening, more cost to handle
legal costs. It is bad for company since give negative impact in their legacy.
• Company
also incurred more cost in advertising to give explanation to the public about
what happen.
Finance and accounting
• Inaccurate
financial report since the actual value of revenue and profit inaccurate
recorded.
• Give
impact of financial planning and investment.
• The
project is delayed, suppose fully operational in early 2011 but it still not
fully operational and incurred more cost.
Management
• Wrong
decision making of having IBM to develop the software as the bad experience IBM
performance in inventory management.
• The
service give by IBM is bad and disappointment.
• Need
to train all employees with new technology.
Customer
• Mostly
affected.
• System
also not user friendly, Austin portal also always have problem, customer cant
access account information.
• Company
also doesn't think of their preference such as ability to choose time of the
month that customer prefers to pay bills.
QUESTION 3 :
To what degree was IBM
responsible for the problem countered by
the Austin Energy billing project?
ANSWER:
• IBM
not really responsive to the problems.
• It
made Austin Energy appealed so many times to IBM officials ranging from the
managers of billing system project up to IBM CEO.
• IBM
responsible in find the roof of problem, make system correction, test the
latest system version and implement the system.
Was Austin Energy at fault for the problem?
Yes, Austin Energy is at fault for the
problem. It is because:
• Austin
Energy as a user had to be committed to the system.
• Probably,
Austin Energy did not plan very properly in the project to develop the billing
system.
• They
must have clear and proper project management objective which should deal with
five major variables: scope, time, cost, quality and risk.
• The
agreement should clearly define the roles and responsibilities of both party
QUESTION 4 :
What were the specific
organizational or technical factors as well as management factors involve in
this project failure?
ANSWER:
Organizational
• Employee
could not be committed enough and described as if they are alpha tester when
they encountered bugs and issues that never have made it to a live version.
• Unable
to meet customer satisfaction.
• No
realignment internally and externally.
• Caused
vastly on costs that exceed budgets.
• Fail
to meet customer expectation.
• Lost
trust draws customer away.
Technical
• No
specific infrastructure.
• Unreliable
system caused money loss.
• Did
not work closely with third party vendors like oracle.
• Customers
unable to access the system’s online portal.
Management
• No
strategy which cause time slippage.
• No
business solutions.
• Interrelated
with manpower.
• Repeating
mistakes and delays.
• Improper
project management objective.
QUESTION 5 :
Describe the steps Austin
Energy and IBM should have taken to better manage this project.
ANSWER:
Austin Energy and IBM need to develop an
information system plan which indicates :
1. The
direction of system development
• Overview
of plant contents
• Current
and future business organization
• Key
biz process
• Management
strategy
2. The
rationale
• Current
situation and current business organization
• Changing
environment
• Major
goals of the biz plan
• Firm’s
strategic plan
3. The
current systems / situation
• Major
system supporting biz function and process
• Current
infrastructure capabilities
• Difficulties
meeting business requirement
• Anticipated
future demand
4. New
developments to consider
• New
system project
• New
infrastructure capabilities required
5. The
management strategy
• Acquisition
plan
• Milestone
and timing
• Organizational
realignment
• Management
control
6. The
implementation plan
• Anticipated
difficulties in implementation
• Progress
report
7. Budget
requirement
• Requirement
• Potential
saving
• Financing
• Acquisition
cycle
CONCLUSION
Good project management is essential for
ensuring that billing system are delivered on time, on budget and provide business
benefit. Risk assessment are required in order to prevent any chances of
failure encountered without deep consideration and deliberations. Strategies
are vital to be implemented since it is useful for managing project risk and
system implementation.
No comments:
Post a Comment